The Lifecycle of an Offshore Wind Farm: From Planning to Decommissioning

Feb 8, 2025

The Lifecycle of an Offshore Wind Farm: From Planning to Decommissioning
The Lifecycle of an Offshore Wind Farm: From Planning to Decommissioning

Offshore wind farms are becoming a cornerstone of the global renewable energy transition, providing clean electricity while reducing carbon emissions. But building an offshore wind farm is a complex, multi-stage process that requires years of planning, engineering, construction, and maintenance before it eventually reaches decommissioning.


In this guide, we break down the entire lifecycle of an offshore wind farmโ€”from the initial feasibility studies to the final decommissioningโ€”highlighting the key challenges and technologies involved at each stage.


1. Feasibility & Site Selection ๐Ÿ“

Before construction begins, an offshore wind farm must undergo years of planning and feasibility studies to ensure viability. Key considerations include:


๐Ÿ”น Wind Resource Assessment โ€“ Measuring wind speeds, consistency, and energy potential using LiDAR buoys and metocean studies.
๐Ÿ”น Seabed Surveys โ€“ Mapping the seabed to assess soil conditions and environmental impact.
๐Ÿ”น Regulatory Approvals & Permits โ€“ Securing government approvals, environmental impact assessments, and licenses.
๐Ÿ”น Grid Connection Planning โ€“ Identifying how and where the generated electricity will connect to the national power grid.

๐Ÿ›‘ Example: The Dogger Bank Wind Farm in the UK spent over 10 years in feasibility studies before construction began.


2. Design & Engineering ๐Ÿ—๏ธ

Once a site is approved, the project moves into detailed engineering and design. This phase includes:

โœ… Turbine Selection โ€“ Choosing between fixed-bottom or floating wind turbines based on water depth and seabed conditions.
โœ… Foundation Engineering โ€“ Monopile, jacket, or floating foundation designs must be selected and tested.
โœ… Electrical System Design โ€“ Planning inter-array cables, substations, and transmission lines.
โœ… Logistics & Supply Chain Planning โ€“ Sourcing materials, vessels, and construction equipment.

๐Ÿ›‘ Example: Floating wind turbines, like those used in Norwayโ€™s Hywind project, require specialized mooring systems and dynamic cables.


3. Procurement & Manufacturing โš™๏ธ

Building an offshore wind farm requires massive industrial coordination. Key procurement steps include:

๐Ÿ”น Turbine Manufacturing โ€“ Large wind turbines (up to 15 MW per unit) are produced by industry leaders like Siemens Gamesa and Vestas.
๐Ÿ”น Foundation & Substation Fabrication โ€“ Offshore substations and foundations are manufactured at specialized shipyards.
๐Ÿ”น Cable Production โ€“ High-voltage export cables are produced for connecting offshore wind farms to the grid.
๐Ÿ”น Vessel & Port Coordination โ€“ Securing jack-up vessels, cable-lay ships, and logistics ports for installation.

๐Ÿ›‘ Example: A single offshore wind turbine blade can be over 100 meters long, requiring specialized transport and handling.


4. Construction & Installation ๐Ÿšข

Once all components are ready, installation begins at sea. This phase includes:

โœ… Foundation Installation โ€“ Using specialized vessels to install monopiles, jackets, or floating anchors.
โœ… Turbine Assembly โ€“ Jack-up vessels or floating cranes lift and install the turbine towers, nacelles, and blades.
โœ… Cable Laying โ€“ Export cables and inter-array cables are buried beneath the seabed using cable-laying vessels.
โœ… Substation Installation โ€“ Offshore substations collect and transmit electricity to the mainland grid.

๐Ÿ›‘ Example: The Hornsea Wind Farm in the UK required over 200 wind turbines to be installed using heavy-lift vessels.


5. Commissioning & Grid Integration โšก

Before becoming operational, an offshore wind farm must go through commissioning and testing:

๐Ÿ“ System Testing โ€“ Checking turbines, cables, and substations for efficiency and safety.
๐Ÿ“ Grid Synchronization โ€“ Connecting the wind farm to the power grid and ensuring stability.
๐Ÿ“ Final Inspections โ€“ Ensuring compliance with environmental and operational standards.
๐Ÿ“ Power Purchase Agreements (PPAs) โ€“ Contracts with energy buyers to supply renewable electricity.

๐Ÿ›‘ Example: Germanyโ€™s Baltic 2 Wind Farm underwent six months of grid testing before full operation.


6. Operations & Maintenance (O&M) ๐Ÿ”ง

Offshore wind farms require constant maintenance to ensure optimal performance. This includes:

๐Ÿ”น Routine Inspections โ€“ Using drones and ROVs to monitor turbine conditions.
๐Ÿ”น Blade & Gearbox Maintenance โ€“ Repairing wear and tear caused by harsh offshore conditions.
๐Ÿ”น Underwater Inspections โ€“ Checking moorings, foundations, and subsea cables.
๐Ÿ”น Crew Transfer & Logistics โ€“ Using CTVs (Crew Transfer Vessels) and SOVs (Service Operation Vessels) for technician access.

๐Ÿ›‘ Example: The worldโ€™s first autonomous maintenance vessel, the Mayflower Autonomous Ship, is being tested for offshore wind O&M support.


7. Decommissioning & Repowering ๐Ÿ—๏ธโ™ป๏ธ

After 25-30 years of operation, an offshore wind farm faces either decommissioning or repowering:

โœ… Decommissioning: Removing turbines, recycling materials, and restoring the seabed.
โœ… Repowering: Replacing older turbines with next-generation, higher-capacity models.
โœ… Cable Recovery: Safely extracting buried export cables.
โœ… Sustainable Recycling: Developing circular economy solutions for turbine blades and metals.

๐Ÿ›‘ Example: Denmarkโ€™s Vindeby Offshore Wind Farm, the worldโ€™s first offshore wind farm, was decommissioned in 2017 after 25 years.


Seavium: Supporting Every Phase of Offshore Wind Operations ๐ŸŒ๐Ÿšข

At Seavium, we provide the specialized vessels needed for every stage of an offshore wind farmโ€™s lifecycle, from installation to maintenance and decommissioning:

โšก Installation Vessels โ€“ Jack-up vessels, cable-layers, and heavy-lift ships.
โšก O&M Support โ€“ Crew Transfer Vessels (CTVs) and Service Operation Vessels (SOVs).
โšก Decommissioning Assets โ€“ Salvage and subsea recovery vessels.


๐Ÿ“ฉ Looking for the right vessel for your offshore wind project? Contact us today.
๐ŸŒ Explore our fleet: Seavium
๐Ÿ“ง Contact us: sales@seavium.com


๐Ÿ”น Offshore wind is the futureโ€”Seavium is here to power it.

Offshore wind farms are becoming a cornerstone of the global renewable energy transition, providing clean electricity while reducing carbon emissions. But building an offshore wind farm is a complex, multi-stage process that requires years of planning, engineering, construction, and maintenance before it eventually reaches decommissioning.


In this guide, we break down the entire lifecycle of an offshore wind farmโ€”from the initial feasibility studies to the final decommissioningโ€”highlighting the key challenges and technologies involved at each stage.


1. Feasibility & Site Selection ๐Ÿ“

Before construction begins, an offshore wind farm must undergo years of planning and feasibility studies to ensure viability. Key considerations include:


๐Ÿ”น Wind Resource Assessment โ€“ Measuring wind speeds, consistency, and energy potential using LiDAR buoys and metocean studies.
๐Ÿ”น Seabed Surveys โ€“ Mapping the seabed to assess soil conditions and environmental impact.
๐Ÿ”น Regulatory Approvals & Permits โ€“ Securing government approvals, environmental impact assessments, and licenses.
๐Ÿ”น Grid Connection Planning โ€“ Identifying how and where the generated electricity will connect to the national power grid.

๐Ÿ›‘ Example: The Dogger Bank Wind Farm in the UK spent over 10 years in feasibility studies before construction began.


2. Design & Engineering ๐Ÿ—๏ธ

Once a site is approved, the project moves into detailed engineering and design. This phase includes:

โœ… Turbine Selection โ€“ Choosing between fixed-bottom or floating wind turbines based on water depth and seabed conditions.
โœ… Foundation Engineering โ€“ Monopile, jacket, or floating foundation designs must be selected and tested.
โœ… Electrical System Design โ€“ Planning inter-array cables, substations, and transmission lines.
โœ… Logistics & Supply Chain Planning โ€“ Sourcing materials, vessels, and construction equipment.

๐Ÿ›‘ Example: Floating wind turbines, like those used in Norwayโ€™s Hywind project, require specialized mooring systems and dynamic cables.


3. Procurement & Manufacturing โš™๏ธ

Building an offshore wind farm requires massive industrial coordination. Key procurement steps include:

๐Ÿ”น Turbine Manufacturing โ€“ Large wind turbines (up to 15 MW per unit) are produced by industry leaders like Siemens Gamesa and Vestas.
๐Ÿ”น Foundation & Substation Fabrication โ€“ Offshore substations and foundations are manufactured at specialized shipyards.
๐Ÿ”น Cable Production โ€“ High-voltage export cables are produced for connecting offshore wind farms to the grid.
๐Ÿ”น Vessel & Port Coordination โ€“ Securing jack-up vessels, cable-lay ships, and logistics ports for installation.

๐Ÿ›‘ Example: A single offshore wind turbine blade can be over 100 meters long, requiring specialized transport and handling.


4. Construction & Installation ๐Ÿšข

Once all components are ready, installation begins at sea. This phase includes:

โœ… Foundation Installation โ€“ Using specialized vessels to install monopiles, jackets, or floating anchors.
โœ… Turbine Assembly โ€“ Jack-up vessels or floating cranes lift and install the turbine towers, nacelles, and blades.
โœ… Cable Laying โ€“ Export cables and inter-array cables are buried beneath the seabed using cable-laying vessels.
โœ… Substation Installation โ€“ Offshore substations collect and transmit electricity to the mainland grid.

๐Ÿ›‘ Example: The Hornsea Wind Farm in the UK required over 200 wind turbines to be installed using heavy-lift vessels.


5. Commissioning & Grid Integration โšก

Before becoming operational, an offshore wind farm must go through commissioning and testing:

๐Ÿ“ System Testing โ€“ Checking turbines, cables, and substations for efficiency and safety.
๐Ÿ“ Grid Synchronization โ€“ Connecting the wind farm to the power grid and ensuring stability.
๐Ÿ“ Final Inspections โ€“ Ensuring compliance with environmental and operational standards.
๐Ÿ“ Power Purchase Agreements (PPAs) โ€“ Contracts with energy buyers to supply renewable electricity.

๐Ÿ›‘ Example: Germanyโ€™s Baltic 2 Wind Farm underwent six months of grid testing before full operation.


6. Operations & Maintenance (O&M) ๐Ÿ”ง

Offshore wind farms require constant maintenance to ensure optimal performance. This includes:

๐Ÿ”น Routine Inspections โ€“ Using drones and ROVs to monitor turbine conditions.
๐Ÿ”น Blade & Gearbox Maintenance โ€“ Repairing wear and tear caused by harsh offshore conditions.
๐Ÿ”น Underwater Inspections โ€“ Checking moorings, foundations, and subsea cables.
๐Ÿ”น Crew Transfer & Logistics โ€“ Using CTVs (Crew Transfer Vessels) and SOVs (Service Operation Vessels) for technician access.

๐Ÿ›‘ Example: The worldโ€™s first autonomous maintenance vessel, the Mayflower Autonomous Ship, is being tested for offshore wind O&M support.


7. Decommissioning & Repowering ๐Ÿ—๏ธโ™ป๏ธ

After 25-30 years of operation, an offshore wind farm faces either decommissioning or repowering:

โœ… Decommissioning: Removing turbines, recycling materials, and restoring the seabed.
โœ… Repowering: Replacing older turbines with next-generation, higher-capacity models.
โœ… Cable Recovery: Safely extracting buried export cables.
โœ… Sustainable Recycling: Developing circular economy solutions for turbine blades and metals.

๐Ÿ›‘ Example: Denmarkโ€™s Vindeby Offshore Wind Farm, the worldโ€™s first offshore wind farm, was decommissioned in 2017 after 25 years.


Seavium: Supporting Every Phase of Offshore Wind Operations ๐ŸŒ๐Ÿšข

At Seavium, we provide the specialized vessels needed for every stage of an offshore wind farmโ€™s lifecycle, from installation to maintenance and decommissioning:

โšก Installation Vessels โ€“ Jack-up vessels, cable-layers, and heavy-lift ships.
โšก O&M Support โ€“ Crew Transfer Vessels (CTVs) and Service Operation Vessels (SOVs).
โšก Decommissioning Assets โ€“ Salvage and subsea recovery vessels.


๐Ÿ“ฉ Looking for the right vessel for your offshore wind project? Contact us today.
๐ŸŒ Explore our fleet: Seavium
๐Ÿ“ง Contact us: sales@seavium.com


๐Ÿ”น Offshore wind is the futureโ€”Seavium is here to power it.